WEEKLY MEETINGS

June 28th, 2022 (30 mins via Phone Call)

Meeting discussed progress over most recent trials. Discussed to move forward creating graphs and make attempt for additional trials before deadline 

June 22nd, 2022 (1 hour)

Meeting discussed progress and changes that need to happen in order to reach

deadlines. 

June 4th, 2022 (1.5 hours)

Meeting discussed the progress and expectations as testing is set to begin.

Topics that were discussed were: 

  • Completed atmospheric code

  • Mechanical build status

  • Remaining modules

  • Rain sensor simulation 

May 26th, 2022 (1.5 hours)

Meeting discussed the progress made on the project.

Topics that were discussed, included most parts arrived, are:

  • Revised Flowchart

  • Updated Specifications 

  • Testing Schedule

  • Rain Senso

  • Sign Setup 

  • Joint Atmospheric Sensors Code

  • Next Week Goals

May 19th, 2022 (1 hour)

First meeting of the Senior Design semester. We went over the progress made during the few weeks we had between the two semesters. 

  • Ordered all parts to complete the project.

  • Ran into a few delays on receiving parts.

  • Tested the ordered parts as they came in.

  • Began outlining code needed for the sensors/troubleshooting. 